Objective for IQ of Weighing Balance
To determine that the IQ of Weighing Balance machine perform as intended by repeatedly running the system on its intended schedules and recording all relevant information and data. Results must demonstrate that installation consistently meets per-determined specifications under normal condition, and where appropriate the worst case situations.
TABLE OF CONTENT
| PARTICULARS | PAGE NO. |
| TITLE PAGE | |
| TABLE OF CONTENT | |
| OBJECTIVE | |
| SCOPE | |
| PRE APPROVAL OF DOCUMENTS | |
| SCOPE OF SUPPLY | |
| BRIEF PROCESS DESCRIPTION | |
| TECHNICAL SPECIFICATION | |
| TECHNICAL SPECIFICATION OF THE COMPONENTS | |
| REQUIRED UTILITIES | |
| INSTALLATION QUALIFICATION PROCEDURE | |
| SAFETY FEATURES & ALARAM | |
| POST APPROVAL OF DOCUMENTS | |
| LIST OF ABBREVIATIONS |
Scope
The scope of this qualification document is to perform the installation qualification to verify the installed components as described in IQ.
Pre Approval Of Documents
Prepared by
| Designation | Name | Date | Signature |
| Executive/Officer Engineering |
Reviewed By
| Designation | Name | Date | Signature |
| Head Engineering | |||
| Head Production |
Approved by
| Designation | Name | Date | Signature |
| Head QA |
Scope Of Supply:
| Description | Specification |
| Model/Serial No. | |
| Control system | 220volts, Single phase power supply |
Brief Process Description:
A Weighing Balance is an an instrument that is used to determine the weight or mass of an object. It is available in a wide range of sizes with multiple weighing capacities and is an essential tool in laboratories, commercial kitchens and Pharmacies.
Technical specification for IQ of Weighing Balance:
| Utility/ Parameter | Specification |
| Model/serial No. | As per URS |
| Electrical Utility | Voltage: 220 VAC ± 5% |
| Frequency: 50 Hz ± 2% | |
| Connection: 3 Wire | |
| 1 Phase, 1 Neutral,1Earthing | |
| Dimension | 400×400 MM |
| Enclosure Protection grade | IP21 |
Technical Specification of The Component
Equipment structure:
| Sr. No | Description | Specified | Method of verification | Actual | Checked by |
| 1 | Make/Model | As per URS | |||
| 2 | Machine Size |
Required utilities:
| Utility/ Parameter | Features |
| Electrical Utility | Voltage: 220 VAC ± 5% |
| Frequency: 50 Hz ± 2% | |
| Connection: 3 Wire | |
| Phase: 1 Phase, 1 Neutral,1Earthing |
Installation qualification procedure:
The location and placement of machine shall be verified.
The installation site has been checked for meeting the installation requirements.
All the equipment of the system has been identified and verified.
The availability of purchase documents has been verified and recorded.
The availability of engineering drawings/schematics/Operational manual has been checked.
Physical verification:
| Parameters | Acceptance Criteria | Observation | Remarks | Done by |
| Horizontal levelling of the equipment | Should be perfectly horizontal | |||
| Positioning of the equipment | It should be aligned vertically straight. There should be enough space for maintenance purposes. | |||
| Floor balancing | It should not give any vibration at any corner of the equipment and should be well placed on the floor | |||
| Identification plate | Name of the equipment and/or suppliers name to be available on the equipment | |||
| Surface finish of equipment | Should be smooth and glossy. | |||
| Any physical damage to the equipment / floor or room walls and door. | No physical scratches or damage should be observed | |||
| Properly labeled / Identified /located | Shall be properly Labeled, Identified & located |
Electrical connection verification:
| Parameters | Acceptance Criteria | Observation | Remarks | Done by |
| General method of the electrical wiring | A. No loose hanging cables B. Well-insulated electrical Wirings. C. Located in a safe place well protected from water seepage during machine or floor cleaning and also safe for operator during operation | |||
| Identification Tags. | A Identification tags should available where essential. |
Safety Feature & Alarm
| Safety feature | Function | Identified by/Date |
| Electrical Insulation | Safety | |
| Earthing | To avoid the shock |
Post Approval Of Documents
Prepared by
| Designation | Name | Date | Signature |
| Executive/Officer Engineering |
Reviewed By
| Designation | Name | Date | Signature |
| Head Engineering | |||
| Head Production |
Approved by
| Designation | Name | Date | Signature |
| Head QA |
List Of Abbreviations
| IQ | Installation Qualification |
| DQ | Design Qualification |
| RM | Raw Material |
| mm | Millimetre |
| QA | Quality Assurance |
| V | Volt |
| Hz | Hertz |
| AC | Alternate Current |