IQ of Weighing Balance

Objective for IQ of Weighing Balance

To determine that the IQ of Weighing Balance machine perform as intended by repeatedly running the system on its intended schedules and recording all relevant information and data. Results must demonstrate that installation consistently meets per-determined specifications under normal condition, and where appropriate the worst case situations.

TABLE OF CONTENT

PARTICULARSPAGE NO.
TITLE PAGE 
TABLE OF CONTENT 
OBJECTIVE 
SCOPE 
PRE APPROVAL OF DOCUMENTS 
SCOPE OF SUPPLY 
BRIEF PROCESS DESCRIPTION 
TECHNICAL SPECIFICATION 
TECHNICAL SPECIFICATION OF THE COMPONENTS 
REQUIRED UTILITIES 
INSTALLATION QUALIFICATION PROCEDURE 
SAFETY FEATURES & ALARAM 
POST APPROVAL OF DOCUMENTS 
LIST OF ABBREVIATIONS 

Scope

The scope of this qualification document is to perform the installation qualification to verify the installed components as described in IQ.

Pre Approval Of Documents

Prepared by

DesignationNameDateSignature
Executive/Officer Engineering   

Reviewed By

DesignationNameDateSignature
Head Engineering   
Head Production   

Approved by

DesignationNameDateSignature
Head QA   

Scope Of Supply:

DescriptionSpecification
Model/Serial No.
Control system220volts, Single phase power supply

Brief Process Description:

A Weighing Balance is an an instrument that is used to determine the weight or mass of an object. It is available in a wide range of sizes with multiple weighing capacities and is an essential tool in laboratories, commercial kitchens and Pharmacies.

Technical specification for IQ of Weighing Balance:

Utility/ ParameterSpecification
Model/serial No. As per URS
Electrical UtilityVoltage: 220 VAC ± 5%
Frequency: 50 Hz ± 2%
Connection: 3 Wire
1 Phase, 1 Neutral,1Earthing
Dimension400×400 MM
Enclosure Protection gradeIP21

Technical Specification of The Component

Equipment structure:

Sr. NoDescriptionSpecifiedMethod of verificationActualChecked by
1Make/Model As per URS    
2Machine Size   

Required utilities: 

Utility/ ParameterFeatures
Electrical UtilityVoltage: 220 VAC ± 5%
Frequency: 50 Hz ± 2%
Connection: 3 Wire
Phase: 1 Phase, 1 Neutral,1Earthing

Installation qualification procedure:

The location and placement of machine shall be verified.

The installation site has been checked for meeting the installation requirements.

All the equipment of the system has been identified and verified.

The availability of purchase documents has been verified and recorded.

The availability of engineering drawings/schematics/Operational manual has been checked.

Physical verification:

ParametersAcceptance CriteriaObservationRemarksDone by
Horizontal levelling of the equipmentShould be perfectly horizontal   
Positioning of the equipmentIt should be aligned vertically straight. There should be enough space  for maintenance purposes.   
Floor balancingIt should not give any vibration at any corner of the equipment and should be well placed on the floor   
Identification plateName of the equipment and/or suppliers name to be available on the equipment   
Surface finish of equipmentShould be smooth and glossy.   
Any physical damage to the equipment / floor or room walls and door.No physical scratches or damage should be observed   
Properly labeled / Identified /locatedShall be properly Labeled, Identified & located   

Electrical connection verification:

ParametersAcceptance CriteriaObservationRemarksDone by
General method of the electrical wiringA. No loose hanging cables B. Well-insulated electrical Wirings. C. Located in a safe place well protected from water seepage during machine or floor cleaning and also safe for operator during operation   
Identification Tags.A Identification tags should available where essential.   

Safety Feature & Alarm

Safety featureFunctionIdentified by/Date
Electrical InsulationSafety 
EarthingTo avoid the shock 

Post Approval Of Documents

Prepared by

DesignationNameDateSignature
Executive/Officer Engineering   

Reviewed By

DesignationNameDateSignature
Head Engineering   
Head Production   

Approved by

DesignationNameDateSignature
Head QA   

List Of Abbreviations

IQInstallation Qualification
DQDesign Qualification
RMRaw Material
mmMillimetre
QAQuality Assurance
VVolt
HzHertz
ACAlternate Current