PQ For Tray Dryer       

OBJECTIVE of PQ For Tray Dryer

To determine that the PQ For Tray Dryer perform as intended by repeatedly running the system on its intended schedules and recording all relevant information and data. Results must demonstrate that performance consistently meets pre-determined specifications under normal condition, and where appropriate the worst case situations.

TABLE OF CONTENT

PARTICULARSPAGE NO.
Title page 
Table of contents 
Objective 
Scope 
Re-Qualification Schedule 
Location of equipment 
Validation team & Responsibility 
Pre-approval of documents 
Scope of supply 
Brief Process Description 
Re-Performance Qualification Procedure 
Performance Verification 
Re-Performance Qualification Report 
References 
Result 
Deviation 
Summary 
Conclusion 
Recommendations 
Attachments 
Post approval of document 

SCOPE

To be performed after installation, modification or relocation and for the re-performance at appropriate interval or as per re-qualification planner.

Performance of the tray dryer machine shall be documented for future reference.

Assure that the mass mixer machine performance is adequate to support the process for which the system is intended.

RE-QUALIFICATION SCHEDULE

Frequency

Performance check of the machine should be re-qualified after every 5 years ±2 months.

LOCATION OF EQUIPMENT

The location of the equipment is in granulation room hormone tablet section at company.

Name of EquipmentID No.Room NameSection
Mass Mixer Granulation 

VALIDATION TEAM AND RESPONSIBILITY

DepartmentResponsibility
ProductionPreparation of protocol and compilation of report. Review of protocol and report. Execution of Re-Qualification activities as per the protocol. Responsible for the compliance of  Re-qualification data
EngineeringReview of protocol and report. To assist user/concerned department during Re- qualification activity
Quality ControlReview of protocol and report. Responsible for analysis of samples & evaluations of the test results.
Quality AssuranceReview, approval and certification of the protocol / reports. Execution & approved of re-qualification activities as per the protocol & certification after successful re-qualification of the equipment.

PRE APPROVAL OF DOCUMENTS

Prepared by

DesignationNameDateSignature
Executive/Officer Production   

Checked By

DesignationNameDateSignature
Head Engineering   
Head Production   
Head Quality Control   

Approved by

DesignationNameDateSignature
Head QA   

Scope Of Supply:

DescriptionSpecification
Model  GMP Model
External dimension:- L X W X H- (all in mm)
  Accessories  Door gasket
Exhaust damper
  Control system440 volts, three phase power supply

Brief Process Description of PQ For Tray Dryer:

Material is charged in the mixer through nozzles or feed-hoppers mounted on the top cover of the mixer. Suppose if screw feeder is opted with mixer, then material to be load onto screw feeder and it will feed powder into mixer. Filling to be done about 70 percent of the total volume of the container. This is generally up to the level of the outer ribbon’s tip. After feeding completes then please close the top cover of the mixer and tighten the latches. Now start the machine form the control panel.

During the blending operation, the outer ribbons of the agitator interchange the material from the ends to the center while the inner ribbons transfer the material from the center to ends. Radial movement is achieved because of the rotational motion of the ribbons. The difference in the peripheral speeds of the outer and inner ribbons results in axial movement of the material along the horizontal axis of the mixer. As a result of the radial and the counter-current axial movement, homogenous blending is achieved in short time. Blending is generally performed in 15 to 20 minutes cycle time. Mixing efficiency of mass mixer depends upon particle size and its bulk density. Generally mass mixer with 95% efficiency in most of the cases. Ingredients with similar particle size and bulk densities tend to mix faster as compared to ingredients with variation in these attributes.

After mixing, material is discharged from a discharge valve located at center bottom of container. The discharge can be fitted with any of these valves like slide-gate, butterfly, flush bottom, spherical and other types depending on the application. The operation of the valves can be manual or pneumatically actuated as per requirements

  • Machine rated for continuous operation.
  • Easy loading & unloading storage with process uniformity.
  • All contact parts of SS 316 AISI.
  • All contact parts can easily be dismantled and cleaned for change of product.
  • Technical Details:
  • Outside controls
  • Design as per stringent cGMP requirements.
  • All Contact parts of AISI Stainless Steel 316 Quality
  • All Non contact parts of AISI Stainless Steel 304 Quality
  • Silicon Food Grade seal/ gasket
  • Easy to clean all contact parts

RE-PERFORMANCE QUALIFICATION PROCEDURE

The action of repeating the qualification or reconfirming that process, product or equipment is suitable for a particular position or task.

Availability of product for operates with load to be checked.

The power supply and connected utility was checked before starting re-performance qualification.

The operating functions of control panel switches and buttons were checked before executing the activity.

PERFORMANCE VERIFICATION

Objective of this performance verification is to provide documented evidence that equipment perform as per respective and up to its operating & performance range.

Standard Operating Parameters Verification:

  • Objective of this verification is to provide documented evidence that equipment perform satisfactory as per its standard operating procedure.

 Cleaning check:

Check pointsObservationChecked By (Sign & Date)
Check the cleanliness of the blades  & bowl  of the machine  
Check the cleanliness of internal surface and its gasket.  
Check cleanliness of the door gasket.  
Check the cleanliness of the top lid & discharge area of the machine.  
Check the cleanliness of the external surface of the machine.  

Safety precaution while drying of material:-

Mask and gloves should be wearing during drying of material.

Performance check of the machine/equipment:-

TestAcceptance CriteriaObservationsDone By Sign/DateChecked By Sign/Date
  Check the machine for proper placement.      Machine  should be place in adequate space & there should be enough space     
  Check for the proper of mixing blades in the machine.        Mixing Blades should work properly   
    Check the uniformity of the material during mixing    Mixing blades should cover all the corners & center for proper mixing of material   
    Check the proper fixing of the door gasket.          Door gasket should be properly fixed & damage free.     

Test Method:

Operate the equipment as per Standard Operating Procedure SOP No. __________  for Operation & Cleaning of mass mixer machine and record the performance of the machine.

Read Also – Rapid Mixer Granulator

Testing procedure:

For performance check of the machine, take any 1 batch or products material for dry or wet mixing and check the proper mixing of the material. Uniformity of the material should meet the target level/acceptance criteria. 

Product NameBatch NumberObservation  Checked By  Reviewed By
 
                   

Record the preventive maintenance status of the machine/equipment.

Equipment NameI.D. No.SectionDetail of Preventive Maintenance
Done onDue on
     

Acceptance Criteria:

Equipment/ Machine shall be operating as defined in the standard operating procedure, if differ then record deviation & check the performance of machine.

Uniformity of the product should meet the criteria/ limit specified in the BMR or as per the BMR.

Operation shall be smooth and there should not be any abnormal sound/ noise.

PQ For Tray Dryer REPORT:

  __________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

REFERENCES:  

SOP No.

RESULT:

_____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Checked By (Sign & date):________________

DEVIATION/CHANGE CONTROL

________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Checked By (Sign & date):________________

SUMMARY:

  _______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Written By (Sign & date):________________

CONCLUSION:

      _______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Written By (Sign & date):________________

RECOMMENDATIONS

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Written By (Sign & date):________________

ATTACHMENTS:

         Document name   Reference No.Checked by Sign & Date
   

POST APPROVAL OF DOCUMENTS

Prepared by

DesignationNameDateSignature
Executive/Officer Production   

Checked By

DesignationNameDateSignature
Head Engineering   
Head Production   
Head Quality Control   

Approved by

DesignationNameDateSignature
Head QA   

Leave a comment

error: Content is protected !!